KS2 pupils watching the concrete pour!

Bin store demolition

Erection of temporary fencing, separating the build site from the school

Week 2

13 tonne Excavator arrives on site,

Ready for demolition

Pupils and our new Deputy Head

check out the demolition!

Week 3

Piling starts - Piling forms the very basis of construction; the essential       

support needed for any kind of structure. It is a technique that sets deep foundations for any form of construction work.

Week 5

Trenches are being dug for drainage and services.

Week 6

Week 7

Foundations have been dug and lined    

Continuing with the perimeter dig – complete with snow!

Building work at Sandbrook

Building work for our new 4 classroom extension has now started!  As you are aware as from September 2016 Sandbrook became a 3 form entry school.  We currently have 19 classes spread over Reception to Year 6 and eventually all years will have 3 classes. This will ensure that the current and future pupils of Sandbrook will have a clean, safe and first class educational setting in which to learn.

The build will take around 6 months to complete and when finished it will be a further addition to our beautiful building, which offers children at Sandbrook Community Primary school, one of the best educational environments in the borough.

There pages will take you on a visual journey of the build through every stage, so parents and pupils are able to see just what goes into a build like this!

Here is a drawing of what the completed classrooms will look like.  The first is a view from the playground and the second the view from Hartley Lane.

Front Elevation of the classrooms

Rear elevation of the classrooms

Week 1

Week 4 – Half term – build continues

Week 8

Steel cages are in the process of being laid out

before the concrete is poured

Week 9

Concrete is poured into the foundations.

Week 10

Concrete is poured into the foundations.

Week 11

Gravel is laid on the floor to seal the ground.


Week 12

Pot and beam floor being laid.

Week 13

Christmas Holidays

Week 14

Block and brickwork underway

Week 15 to 18

Block and brickwork really coming on